DLMS/COSEM conformance test maintenance process

The DLMS UA maintains the CTT to eliminate problems with the tool found during testing, to enhance tests and to accommodate changes in the standards.

The recommended procedure is the following:

  1. A proposal, together with a justification is made to add or modify a tests. This can be initiated by any member of the DLMS UA, implementing the specification or by the DLMS UA itself.
  2. The request is investigated by the DLMS UA.
  3. If the request is accepted, test plans are amended by the DLMS UA.
  4. The new tests are implemented by the tool developer.
  5. The new tests are validated by the DLMS UA.
  6. The amended test plans are published.
  7. A new version of the CTT is made available to the licensed tool users.

Requests for modification or adding a test

Date is the day when the request has been received. Send a request.

Test concerned is the number of an existing test in the conformance test plans.

Short description outlines the problem and the proposed modification

File is a link to a full description

Status is pending, approved or rejected.

Date

Test concerned

Short description

Link to file

Status

 

 

 

 

 

 

 

 

 

 

 